Location: Kennedy Space Center
Owner: NASA
Duration: 12 Days
Contract Value: $700,000
General Scope:
Provide emergency repairs and install two replacement pile bents at the Jay-Jay Railroad Bridge. This critical project had a 28-calendar day schedule. Through extensive coordination and expediting efforts, equipment was mobilized, materials were procured and work was completed ahead of schedule.
Performance Evaluation by Owner:
“Your company’s past performance of meeting tight project schedules while performing quality work enabled us to quickly determine the course of action most likely to have given us a chance at meeting this very aggressive schedule of designing, procuring, and implementing the critical repairs in less than one month.” Miguel A. Morales, Chief, Facilities Division.