This 22,000 sq. ft addition and renovation project included the demolition of an existing facility and extensive site work that converted a low lying, unusable area into a retention pond and athletic fields. Additionally, RUSH renovated administration offices, built new offices, physical fitness areas and locker rooms. Other enhancements to the existing facility included a child watch area with an adjoining playground and a substantial renovation to the gymnasium. RUSH gave beneficial occupancy to the YMCA three weeks early and completed the project one week ahead of the original schedule.
RUSH Construction from the very beginning demonstrated its high quality professional approach to getting the work done. Mobilizing a quality staff and outstanding subcontractors on short notice to deliver a quality product on schedule.
– Mark Russell, Chief Financial Officer, Central Florida YMCA
Owner: Central Florida YMCA